Projects

ACL were engaged by Southbase to undertake works at Mt Albert Grammar School that spanned from December 2023 - May 2024.
Another sucessful project in conjunction with Whangārei District Council and Northern Transport Alliance, Asset Construction were engaged to undertake slip repairs on the Paparoa-Oakleigh Road and install a block MSE retaining wall and shear key r
In collaboration with Whangārei District Council and Northern Transport Alliance, Asset Construction carried out footpath improvements and other safety upgrades including raised table construction on Clark Road and Three Mile Bush Road in Kamō.
With a brand new retirement villiage being constructed in a pre-established subdivision in Tikipunga, Whangārei, came the need for a new bus route.
Asset Construction's involvement as the civil contractor specialist on this contract was to provide installation of all storm and waste water lines, installation of manholes, cesspits, threshold drains, attenuation tanks (8 tanks in a total of 190
We commenced work in June 2022 on Silverdale Primary School in conjunction with Southbase Construction.
Our second of three projects in conjunction with Leighs Construction at Botany Downs Primary School as part of our South Auckland Schools Cluster contract.  The job ran from December 2022 through Decemebr 2023, with scheduled works being completed
ACL worked in conjunction with Leighs Construction at Puhinui School as part of our South Auckland Schools Cluster contract.  The job ran from December 2022 through Decemebr 2023, with scheduled works being completed to target.
The walkway and playground ACL worked on through 2022 as part of a larger project in Awataha, Northcote in conjunction with Piritahi, is now open to the public.
Works are now fully complete at our Hobsonville Point site at Catalina Bay. Check out our bespoke concrete planters, a tricky design brief that our team managed to bring into reality.