Final images from our project as part of the landmark extension build of Whangārei Boy's High School that spanned from 2020 - 2024, in conjunction with Leigh's Construction.
Projects
We worked for three months on the construction of a mass structural engineered wall for road stablisation on State Highway 12, in conjunction with Fulton Hogan and NZTA. Main tasks undertaken were bulk earthworks and drainage, all completed succes
ACL were engaged by Southbase to undertake works at Mt Albert Grammar School that spanned from December 2023 - May 2024.
Another sucessful project in conjunction with Whangārei District Council and Northern Transport Alliance, Asset Construction were engaged to undertake slip repairs on the Paparoa-Oakleigh Road and install a block MSE retaining wall and shear key r
In collaboration with Whangārei District Council and Northern Transport Alliance, Asset Construction carried out footpath improvements and other safety upgrades including raised table construction on Clark Road and Three Mile Bush Road in Kamō.
With a brand new retirement villiage being constructed in a pre-established subdivision in Tikipunga, Whangārei, came the need for a new bus route.
Asset Construction's involvement as the civil contractor specialist on this contract was to provide installation of all storm and waste water lines, installation of manholes, cesspits, threshold drains, attenuation tanks (8 tanks in a total of 190
We commenced work in June 2022 on Silverdale Primary School in conjunction with Southbase Construction.
Our second of three projects in conjunction with Leighs Construction at Botany Downs Primary School as part of our South Auckland Schools Cluster contract. The job ran from December 2022 through Decemebr 2023, with scheduled works being completed
ACL worked in conjunction with Leighs Construction at Puhinui School as part of our South Auckland Schools Cluster contract. The job ran from December 2022 through Decemebr 2023, with scheduled works being completed to target.